Flydubai to relocate aircraft from DXB to DWC from early 2027

Dubai Airports CEO confirms staged transition as second runway at Al Maktoum International targets end-2027 completion.

Runway construction and earthworks at airport development site viewed from abovePhotograph by Daniel Ellis on Pexels

Flydubai to begin DWC relocation from early 2027#

Flydubai will relocate five to six aircraft from Dubai International Airport to Al Maktoum International Airport starting in early 2027, Dubai Airports CEO Paul Griffiths said during a media briefing on Thursday. The carrier will be the first airline to shift part of its operations to the airport. The relocation forms the initial stage of a transition that will unfold over multiple years. Al Maktoum International's second runway is scheduled for completion by the end of 2027, Griffiths said. Construction activity is on schedule, with the first phase of the airport expected to deliver capacity for 150 million passengers in the early 2030s.

Transition to unfold gradually over several months#

The transfer of operations from Dubai International to Al Maktoum International will take place gradually over several months, Griffiths said. Emirates and flydubai will use capacity at the new airport as Dubai International approaches its operating limit. Other airlines will transfer later. The full relocation of Dubai International operations is planned once the first 150 million-passenger phase at Al Maktoum International is available. Griffiths referenced Hong Kong's airport transfer in the late 1990s, when an airport handling approximately 20 million passengers moved operations to a new site in 24 hours. Dubai's transfer will take longer due to the larger passenger volumes involved, he said.

Two runways planned for initial 150 million-passenger phase#

Two runways will be required for the first 150 million-passenger phase at Al Maktoum International, Griffiths said. The third and fourth runways will be constructed as terminal capacity expands. The fifth runway will operate as a standby when one of the others is out of service. The completed airport is planned to have five runways and capacity for up to 260 million passengers annually. The initial development includes up to eight passenger processing nodes, each delivering capacity for approximately 31 million to 32 million passengers. Those nodes can be constructed ahead of demand, Griffiths said.

Earthworks and piling activity underway at site#

Earthworks and piling activity are taking place across the Al Maktoum International site, Griffiths said. The plan includes further sections constructed as demand increases. Dubai World Central will deliver the additional capacity required once Dubai International reaches its operating limit. Slots at Dubai International will be freed up for further expansion before other airlines begin their transfer. Once the airport reaches its 150 million-passenger capacity, all of Dubai International's operations are planned to relocate to Al Maktoum International, Griffiths said.

Sources2 sources across 2 domains

  1. gulfnews.comGulf NewsSecond runway completion targeted for end of 2027, first phase capacity of 150 million passengers expected in early 2030s, five runways planned with capacity for 260 million passengers, earthworks and piling activity underway
  2. khaleejtimes.comKhaleej TimesFlydubai to relocate five to six aircraft from early 2027, Paul Griffiths confirmed staged transition during media briefing on Thursday, comparison with Hong Kong airport transfer, two runways sufficient for initial phase

Each source above carries the claim it supports. Links open the publisher's own page; their text is not reproduced here beyond what the claim requires, and their rights remain theirs.

Filed underflydubaial maktoum internationaldubai airportsdwc expansionairline relocationairport capacity

Arab Time is published by Arabian Media Network. Pieces are produced by the Hospitality Capital Desk with AI-assisted synthesis of the cited sources and automated verification against the network's editorial policy. Every piece carries a desk rather than a reporter. Corrections are recorded on the piece and on the corrections page.

The dataset behind this storyThe Pipeline

Every announced MENA hotel, resort and destination project, with announced versus delivered tracked over time.

31 rowsverified 3 September 2026CSV

More from the Hospitality Capital Desk

The desk